How the score is calculated
Worksynk's score is rule-based rather than predictive. Every project starts at 100, and each detectable problem subtracts a capped number of points, so no single signal can swamp the rest:
- Overdue open items: up to 35 points, scaling with the share of open work past its due date.
- Items waiting on dependencies that are still open: up to 25 points.
- Stale items nobody has touched in three days: up to 15 points.
- Unassigned high or critical work: 5 points each, up to 15.
- Items stuck in review for more than two days: up to 10 points.
How to read it
Scores fall into four bands: Healthy (80 and above), Watch (60 to 79), At risk (40 to 59) and Critical (below 40). A single number means little on its own, so the score is captured once a day per active project and read as a trend.
It is a decision aid, not a forecast: when it drops, the factor list tells you which rule fired and which work items to look at.